WIELAND is proud to share its ongoing progress on the Magna Electric Vehicle Structures (M.E.V.S) Phase II plant in St. Clair, MI. WIELAND completed the 370,000 SF Phase I plant in January 2022, and soon after, broke ground on the 744,000 SF Phase II addition. The original plant houses Magna’s battery enclosure line while Phase II provides greater e-coating and production capabilities, along with extra warehouse storage. WIELAND commenced construction in July 2022, and projects to finish the project in late spring 2024.